Built by SWS Indonesia — the PDG JC3 Data Center in Cikarang, Bekasi, Indonesia.

I. Key Facts

  • Full project name: PDG JC3 hyperscale AI data center in Cikarang, Bekasi, Indonesia
  • Exact location: Sukamahi Village, Cikarang, Bekasi Regency, West Java — GIIC Greenland International Industrial Park (Deltamas)
  • Investor: Princeton Digital Group (PDG), Singapore; General contractor: China Construction Eighth Engineering Division (Shanghai Construction Overseas), EPC general contracting
  • Contract value: RMB 5.5 billion — a benchmark single-building hyperscale IDC project in Southeast Asia
  • Construction start: November 2025; main steel structure topped out in April 2026

II. Scale & Power Infrastructure

  • Total floor area: 93,500 m², a dual-data-center cluster (DC1 + DC2)
  • Total IT power capacity: 120 MW, supplied by a dedicated 150 kV Sukamahi GI substation
  • Power configuration: dual-circuit 150 kV high-voltage plus 20 kV low-voltage redundancy with N+1 uninterrupted protection; design PUE < 1.4

III. Scope of Work

Piling, steel structure main frame, civil works, outdoor pipe networks, fire protection, high- and low-voltage electrical systems, UPS, low-voltage and security systems, refrigeration and HVAC, and full mechanical and electrical installation and commissioning.

IV. Project Positioning

A core computing hub for Greater Jakarta, serving Amazon, Microsoft, Southeast Asian cross-border cloud, and AI supercomputing — a benchmark for China–Indonesia Belt and Road digital infrastructure.

(Company address and corporate profile: awaiting content)